CASE / CLAYSON EDI

Suez EDI Module Repair and GE EDI Stack Maintenance for Everbright Energy

In November 2023 Clayson won the contract to repair 20 Suez 5T EDI modules for Everbright Biomass Thermal Power (Lu'an). Factory inspection found resin and membrane oxidation caused by excess residual chlorine. Clayson optimised the system, repaired the modules and commissioned them on site.

▦ Case Studies / Project Record ◷ Published 2026-11-16 15:20:00 ◉ Views 3 Back to Case Studies →
Project DetailsPROJECT DETAILS

Suez EDI module repair and GE EDI stack maintenance for Everbright Energy

EDI stacks returned to the Clayson factory for inspection

EDI system reinstallation and commissioning on site

In November 2023 Quanzhou Clayson Automation Technology Co., Ltd. won the contract to repair 20 Suez 5T EDI modules for Everbright Biomass Thermal Power (Lu'an) Co., Ltd. Factory inspection found that excess residual chlorine had oxidised the resin and membranes, reducing module flux. Clayson optimised the complete ultrapure water system, repaired the EDI modules, and its engineers reinstalled and commissioned them, bringing the EDI project into smooth operation.

GET A SOLUTION

Off-spec EDI product water and frequent alarms?

Stack repair, replacement and system optimisation, with a 1-to-1 proposal for your conditions.

Call Now +86 400-862-1862
Online Support
Contact

Hotline

+86 18017752343

Business Hours

Monday - Friday

Office

+86 400-862-1862

QR Code
WeChat QR Code
CHAT